Exploratory study of the dimensions of risks in civil construction projects
DOI:
https://doi.org/10.33448/rsd-v10i7.16452Keywords:
Exploratory factor analysis; Risk categories; Risk events; Risk factors; Construction projects.Abstract
This article aims to deepen the analysis of the risk elements present in construction projects, identifying, detailing, evaluating, and classifying the most relevant events present in this complex and dynamic environment. The central issue highlighted in the study considers the presence of risk elements and their relative impacts on construction projects, especially in aspects related to meeting schedules and budgets. To answer the problem mentioned, an exploratory survey of the Survey type was developed together with a non-probabilistic sample, characterized by 105 engineers and professionals who work with themes related to risk management in the Brazilian construction sector, complemented by a multivariate statistical analysis, under the framework of exploratory factor analysis. The results point to a distribution and classification of the observed elements, where 205 risk events are configured, properly classified by categories and factors. This detail makes it possible to assist future approaches that need, through the level of importance, to dimension and measure, in a more detailed way, potential aspects of risk present in projects destined to constructive undertakings.
References
Aaker, D., Kumar, V. & Day, G. S. (2004) Pesquisa de Marketing. São Paulo: Atlas.
Bissacot, T. C. C. & Oliveira, S. M. A. C. (2016) Instrumento para o gerenciamento de riscos ambientais. Engenharia Sanitária e Ambiental, v.21, n.2, p 227-232. DOI: 10.1590/S1413-41522016140442.
Brasil. (2013) Lei 12.846/2013, de 1 de agosto de 2013. Lei Anticorrupção ou Lei da Empresa Limpa. Brasília: Diário Oficial da União.
Britto Jr, A. & Feres Jr, N. A. (2011) Utilização da técnica da entrevista em trabalhos científicos. Evidência, v. 7, n. 7, p 237-250.
Bu-Qammaz, A. S., Dikmen, I. & Birgonul, M. T. (2009) Risk assessment of international construction projects using the analytic network process. Canadian Journal of Civil Engineering, v 36, n. 7, p 1170-1181. DOI: https://doi.org/10.1139/L09-061.
Caiado, R. G. G. (2015) Diretrizes para Maturidade da Gestão de Risco em Projetos de Construção. Dissertação (mestrado) - Universidade Federal Fluminense: Escola de Engenharia, Niterói.
CBIC – Câmara Brasileira da Indústria da Construção. (2016) Guia de Ética e Compliance para Instituições e Empresas do Setor da Construção - Ética e Compliance na Construção. Brasília: CBIC.
Creswell, J. W. (2012) Qualitative Inquiry and Research Design: Choosing Among Five Approaches. Thousand Oaks, CA: Sage.
Fallahnejad, M. H. (2012) Delay Causes in Iran Gas Pipeline Projects. International Journal of Project Management, v. 31, n. 1, p 136-146. DOI: 10.1016/j.ijproman.2012.06.003.
Farrokhi, F. & Mahmoudi-Hamidabad, A. R. (2012) Rethinking Convenience Sampling: Defining Quality Criteria. Theory and Practice in Language Studies, v. 2, n. 4, p 784-792. DOI:10.4304/tpls.2.4.784- 792.
Ferreira, B. A. A., Almeida, J. O. R. Leão, P. R. C. & Silva, N. P. G. (2012) Gestão de Riscos em Projetos: Uma Análise Comparativa da Norma ISO 31000 e o Guia PMBOK. Revista de Gestão e Projetos, v. 4, n. 3, p 46-72. DOI: 10.5585/gep.v4i3.173.
Freitas, A. P. F. (2018) Metodologia de Gerenciamento de Riscos na Indústria da Construção Civil: Aplicação em empresas de micro e pequeno portes. Tese (doutorado) - Universidade Federal Fluminense: Escola de Engenharia, Niterói.
Fugar, F. D. K. & Agyakwah-Baah, A. B. (2010) Delays in Building Construction Projects in Ghana. Australasian Journal of Construction Economics and Building, v. 10, n. 1/2, p 103-116, 2010.
Garvey, P.R. (2009) Analytical methods for risk management: A systems engineering perspective. Boca Raton: CRC Press, p 1-12.
González, P., Gonzalez, V., Molenaar, K. & Orozco, F. (2014) Analysis of Causes of Delay and Time Performance in Construction Projects. Journal of Construction Engineering and Management, v. 140, n. 1, 04013027. DOI: 10.1061/(ASCE)CO.1943-7862.0000721.
Guimarães, P. R. B. (2008) Métodos Quantitativos Estatísticos. Curitiba: IESDE Brasil S.A.
Hayes, B. (1997) Measuring Customer Satisfaction: Survey Design, Use, and Statistical Analysis Methods. 2ª Ed. Milwaukee: Quality Press.
Hair JR, J. F., Black, W. C., Babin, B. J. & Anderson R. E. (2014) Multivariate Data Analysis. Pearson International Education Limited: Edinburg.
Hauck-Filho, N., Teixeira, M. A. P., Machado, W. L. & Bandeira, D. R. (2012). Marcadores reduzidos para a avaliação da personalidade em adolescentes. Psico-USF, 17(2), 253-261.
Hwang, B.G. & Zhao, X. (2013) Identifying the Critical Factors Affecting Schedule Performance of Public Housing Projects. Habitat International, v. 38, p 214-221. DOI: https://doi.org/10.1016/j.habitatint.2012.06.008.
Leech, N., Barret, K. & Morgan, G. A. (2005) SPSS for intermediate statistics: use and interpretation. Lawrence Erlbaum Associates: New Jersey.
Le-Hoai, L., Lee Y. D. & Lee J. Y. (2008) Delay and Cost Overruns in Vietnam Large Construction Projects: a comparison with other selected countries. Ksce Journal of Civil Engineering, v. 12, n. 6, p. 367-377. DOI 10.1007/s12205-008-0367-7.
Liu, Y., Liu, Y., Li, H., Fu, X., Guo, H., Meng, R., Lu, W., Zhao, M. & Wang, H. (2016) Health risk impacts analysis of fugitive aromatic compounds emissions from the working face of a municipal solid waste landfill in China. Environment International, v. 97, p 15-27. DOI: https://doi.org/10.1016/j.envint.2016.10.010.
Lorenzo-Seva, U. & Ferrando, P. J. (2019). Robust Promin: a method for diagonally weighted factor rotation. Technical report, URV. Tarragona: Spain.
Marcelli, M. (2007) Sinistros na Construção Civil: Causas e Soluções Para Danos e Prejuízos em Obras. São Paulo: Pini.
Muianga, E. A. D., Granja, A. D. & Ruiz, J. A. (2015) Desvios de custos e prazos em empreendimentos da construção civil: categorização e fatores de influência. Ambiente Construído, v. 15, n. 1. DOI: http://dx.doi.org/10.1590/S1678-86212015000100008.
Muya-Mundia, C. K., Sichombo, B. & Shakantu, W. (2013) Cost Escalation, Schedule Overruns and Quality Shortfalls on Construction Projects: The Case of Zambia. International Journal of Construction Management, v. 13, n. 1, p 53-68. DOI: https://doi.org/10.1080/15623599.2013.10773205.
Nadoushani, Z. S. M., Hammad, A. W. A. & Akbarnezhad, A. (2018) Closure to Location Optimization of Tower Crane and Allocation of Material Supply Points in a Construction Site Considering Operating and Rental Costs. Journal of Construction Engineering and Management. v. 144, Issue 11. DOI: https://doi.org/10.1061/(ASCE)CO.1943-7862.0001558.
Najafabadi, E. & Pimplikar, D. (2013) The Significant Causes and Effects of Delays in Ghadir 2206 Residential Project. Journal of Mechanical and Civil Engineering, v. 7, n. 4, p 75-81.
Nutakor G. (2007) Assessing final cost of construction at bid time. Cost Engineering, v. 49, n. 11, p 10-16.
Oliveira, E. P. de, Santos, J. A. N. dos, Freitas, A. P. A. & Neves, S. F. M. (2021) Corruption in Brazil: Analysis of transparency from the perspective of the civil construction sector. Research, Society and Development, v. 10, n. 5, p e46310515257. DOI: 10.33448/rsd-v10i5.15257.
Oliveira, N. L. F. (2018) Análise de Riscos em Empreendimentos de Construção Civil no Brasil: Um Método de Aferição. Tese (doutorado) - Universidade Federal Fluminense: Escola de Engenharia, Niterói.
Pinca, D. F. & Rozzetto D. S. (2018) Interrupções em projetos de engenharia consultiva em cenário de desestruturação organizacional. Revista iPecege, v. 4, n. 2, p 54-61. DOI: 10.22167/r.ipecege.2018.2.54.
Rahman, I. A., Memon, A. H. & Karim, A. T. A. (2013) Relationship between Factors of Construction Resources Affecting Project Cost. Modern Applied Science, v. 7, n. 1, p 67-75. DOI:10.5539/mas.v7n1p67.
Ramanathan, C., Narayanan, S. P. & Idrus, A. B. (2012) Construction delays causing risks on time and cost - a critical review. Australasian Journal of Construction Economics and Building, v. 12, n. 1, p 37-57, 2012. DOI: https://doi.org/10.5130/AJCEB.v12i1.2330.
Rezakhani, P. (2012) Classifying Key Risk Factors in Construction Projects. The Bulletin of the Polytechnic Institute of Jassy, Construction. Architecture Section, v. 58, n. 2, p 27-38.
Ricardino, R., Silva, S., & Alencar, C. (2013) Causas Frequentes de Reivindicações Contratuais. Revista Engenharia, v. 70, n. 615, p 90-94.
Rosenfeld, Y. (2014) Root-Cause Analysis of Construction-Cost Overruns. Journal of Construction Engineering and Management, v. 140, n. 1, p 04013039. DOI: https://doi.org/10.1061/(asce)co.1943-7862.0000789.
Shehu, Z., Endut, I. R. & Akintoye, A. (2014) Factors Contributing to Project Time and Hence Cost Overrun in the Malaysian Construction Industry. Journal of Financial Management of Property and Construction, v. 19, n. 1, p 55-75. DOI: https://doi.org/10.1108/JFMPC-04-2013-0009.
Shi, B., Jiang, J., Liu, R., Khan, A. U. & Wang, P. (2017) Engineering risk assessment for emergency disposal projects of sudden water pollution incidents. Environmental Science and Pollution Research, n 24, p 14819– 14833. DOI: 10.1007/s11356-017-9078-2.
Silva V. F. (2012) Análise de Risco na Construção – Guia de Procedimentos para Gestão. Dissertação (mestrado) - Universidade do Porto, Faculdade de Engenharia.
SUSEP – Superintendência de Seguros Privados. (2011) Circular SUSEP nº 519, de 17 de janeiro de 2011. Brasília: SUSEP.
SUSEP – Superintendência de Seguros Privados. (2016) Circular SUSEP nº 540, de 14 de outubro de 2016. Brasília: SUSEP.
Timmerman, M. E. & Lorenzo-Seva, U. (2011). Dimensionality Assessment of Ordered Polytomous Items with Parallel Analysis. Psychological Methods, 16, 209-220. doi:10.1037/a0023353.
Wang, J. & Yuan, H. (2011) Factors affecting contractors’ risk attitudes in construction projects: Case study from China. International Journal of Project Management, v. 29, n. 2, p 209-219. DOI: 10.1016/j.ijproman.2010.02.006.
Zou, P. X. W., Zhang, G. & Wang, J. (2007) Understanding the Key Risks in Construction Projects in China. International Journal of Project Management, v. 25, n. 6, p 601-614. DOI: https://doi.org/10.1016/j.ijproman.2007.03.001.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2021 Andrey Pimentel Aleluia Freitas; João Alberto Neves dos Santos; Eliã Pereira de Oliveira; Danilo Rangel Fernandes; Nylvandir Liberato Fernandes de Oliveira
This work is licensed under a Creative Commons Attribution 4.0 International License.
Authors who publish with this journal agree to the following terms:
1) Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
2) Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
3) Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work.